4401 Contracts, collateral and security are enforceable.
4403 Contracts, collateral and security are enforceable.
4405 Contracts, collateral and security are considered enforceable even if certain non-key issues may exist.
4407 There are unresolved key issues in respect of actual enforcement of contracts, collateral and security.
4409 Transaction characteristics
4411 Design and technology risk.
4413 Fully proven technology and design.
4415 Fully proven technology and design.
4417 Proven technology and design — start-up issues are mitigated by a strong completion package.
4419 Unproven technology and design; technology issues exist and/or complex design.
4423 Permitting and siting.
4425 All permits have been obtained.
4427 Some permits are still outstanding but their receipt is considered very likely.
4429 Some permits are still outstanding but the permitting process is well defined and they are considered routine
4431 Key permits still need to be obtained and are not considered routine. Significant conditions may be attached.
4433 Type of construction contract.
4435 Fixed-price date-certain turnkey construction EPC (engineering and procurement contract).
4437 Fixed-price date-certain turnkey construction EPC.
4439 Fixed-price date-certain turnkey construction contract with one or several contractors.
4441 No or partial fixed-price turnkey contract and/or interfacing issues with multiple contractors.
4443 Completion guarantees.
4445 Substantial liquidated damages supported by financial substance and/or strong completion guarantee from sponsors with excellent financial standing.
4447 Significant liquidated damages supported by financial substance and/or completion guarantee from sponsors with good financial standing.
4449 Adequate liquidated damages supported by financial substance and/or completion guarantee from sponsors with good financial standing.
4451 Inadequate liquidated damages or not supported by financial substance or weak completion guarantees.
4453 Track record and financial strength of contractor in constructing similar projects.
4465 Scope and nature of operations and maintenance (O&M) contracts.
4467 Strong long-term O&M contract, preferably with contractual performance incentives, and/or O&M reserve accounts.
4469 Long-term O&M contract, and/or O&M reserve accounts.
4471 Limited O&M contract or O&M reserve account.
4473 No O&M contract: risk of high operational cost overruns beyond mitigants.
4475 Operator’s expertise, track record, and financial strength.
4477 Very strong or committed technical assistance of the sponsors.
4483 Limited/weak or local operator dependent on local authorities.
4487 If there is a take-or-pay or fixed-price off-take contract:
4489 Excellent creditworthiness of off-taker; strong termination clauses; tenor of contract comfortably exceeds the maturity of the debt.
4491 Good creditworthiness of off-taker; strong termination clauses; tenor of contract exceeds the maturity of the debt.
4493 Acceptable financial standing of off-taker; normal termination clauses; tenor of contract generally matches the maturity of the debt.
4495 Weak off-taker; weak termination clauses; tenor of contract does not exceed the maturity of the debt.
4497 If there is no take-or-pay or fixed-price off-take contract:
4499 Project produces essential services or a commodity sold widely on a world market; output can readily be absorbed at projected prices even at lower than historic market growth rates.